Question of the week. Question of the week. *How long does it take to get started on digging a basement of a new home?
First meeting to digging the basement of your new “Truly Custom” home. (TIMELINE) Initial meet and greet (As soon as you call us) “This Week?” Land acquisition (Varies, Do you own land already? Building on land we own? Need us to buy the land on your behalf? Or do we need to find that perfect spot elsewhere?) “Average 1-2 weeks”. Home design (Varies, Do you have a plan? Are we starting from scratch? Starting from one of our previous plans?) “Average 2-4 weeks”. Completion of specifications that match plans. (25 pages+ of granular detail to ensure all expectations are met) “Average 2 weeks to ensure it’s perfected”. Completion of whole contract package (which includes land details, plans, and final specification sheet.). “3-5 days.” Back end permits, banking, and other jurisdictional requirements. (Is there an hoa? Do we need to do soil testing?) “4-6 weeks” Total time from first meet to digging your basement of a “truly custom” home? Varies, but on the short side of the average, 2-3 months is realistic, and that’s on the short side of the averages, not taking into consideration our Midwestern weather. Don’t fall for signing a contract on the spot and being told something that’s just not true. Do you want your home built in the same short high pressure manner, or do you want your home built with proper planning & preparation? Thinking of a spring build? Don’t wait, NOW’S the time to make that first call. Calling Now + Timeline above = April (ish)! Don’t wait! 816-739-1444 www.grantscustomhomes.com
0 Comments
Your comment will be posted after it is approved.
Leave a Reply. |
Grants Custom Homes
Categories |